Yet another Stage of V.I. Grayfer Field Development Facilities Construction Completed
ENG
РУС

Yet another Stage of V.I. Grayfer Field Development Facilities Construction Completed

Mar 20, 2022 г.
All news

LQP Topside Onshore Assembly and Loading-out onto Transportation Barge Completed

In March 2022 Company completed load-out of the Living Quarters Platform (LQP) Topside (TS) for V.I. Grayfer field onto the transportation and installation barge.

The weight of the topside and transportation and installation frame is more than 2000 tons. The module construction readiness during load-out is more than 97%, the remaining works relate to interface connections with other key elements of the field development project – the Living Quarters Platform Substructure, the Ice-resistant Fixed Platform (IRP) Topside and the Connecting Bridge.

LQP TS installation onto the substructures erected at the field in 2020 is scheduled for April this year.